中文摘要: |
以向莆铁路FJ-3A标尤溪大桥1-140 m劲性骨架拼装施工为依托,阐述大吨位塔机分节吊装,采用千斤顶斜拉扣挂法悬臂拼装铁路桥劲性骨架施工技术。 |
英文摘要: |
Based on the Youxi Bridge in FJ 3A section during Xiang Pu Railway, the assembly construction of the 1 140 stiff framework is introduced in this paper, with focus on the large tonnage tower crane hoisting jack sections and cable stayed suspension method for cantilever erection of railway bridge with stiff skeleton construction technology. |
冯文山.大吨位塔机悬臂拼装上承式拱桥劲性骨架施工技术[J].石家庄铁道大学学报(自然科学版),2012,(3):38-41,77. |