客运专线预制箱梁后浇翼缘板施工技术
Construction Technology of Post casting Flange Plate for Pre cast Box Beams of Passenger Dedicated Line
投稿时间:2011-11-15  
中文关键词:客运专线  双线整孔预制箱梁  现浇翼缘板
英文关键词:passenger dedicated line  double line and full span prefabricated box beams  cast in place flange plate
基金项目:
作者单位
苏中华 中铁十二局集团 第三工程公司 
摘要点击次数: 1455
全文下载次数: 1449
中文摘要:
      由于受隧道施工限界影响,客运专线双线整孔预制箱梁无法通过隧道,预制时先切除两侧部分翼缘板,待架设后再现浇切除部分翼缘板。介绍了切除翼缘板箱梁现浇施工支架的设计和关键施工技术,可为同类预制梁施工提供技术参考。
英文摘要:
      Due to the effects of construction gauge of the tunnels, double line integral arch box girders in passenger dedicated lines cant go through the tunnel, and must be prefabricated by pre cutting of partial flange plate on both sides, which is to be cast after the erection. This article describes key design and construction technique for casting the removed flange plate of box girder, and provides reference for similar pre cast girder construction.