JQ900A型架桥机通过万宁2号拱桥方案研究
Study on JQ900A Bridge Construction Machine Passing Tied Arch in Wanning 2nd Bridge
投稿时间:2010-09-03  
中文关键词:系杆拱桥  架桥机  施工方案  结构分析
英文关键词:tied arch bridge  bridge machine  construction project  structural analysi
基金项目:
作者单位
刘林生 中铁十九局集团 第五工程有限公司 
摘要点击次数: 1236
全文下载次数: 1153
中文摘要:
      介绍了万宁2号特大桥上JQ900A架桥机和KSC900运梁车过桥施工方案,采用结构分析程序对主梁的结构受力进行分析,计算了不同工况下主梁顶板、底板的应力,计算分析结果表明:抗裂安全系数均大于1.1,最大弯矩处的截面强度安全系数大于2.2,过桥方案是合理可行的。
英文摘要:
      The bridge machine JQ900A and the transporting girder vehicle KSC900 passing the Wanning 2nd super large bridge is introduced. The structural behavior is analyzed with Sap2000 and Midas/Civil, and the stress of the top and bottom flange of main beam is calculated. The calculation results show that, under every load condition, the anti cracking safety factors are all lager than 1.1, and the strength safety factors at the maximum bending moment are all lager than 2.2, which indicates that the project is reasonable and feasible.
刘林生.JQ900A型架桥机通过万宁2号拱桥方案研究[J].石家庄铁道大学学报:自然科学版,2010,(4):95-.
查看全文  查看/发表评论  下载PDF阅读器